JSC Atomstroyexport together with the Russian and Slovak enterprises takes part in completion of Mohovce NPP Units 3&4, which construction was started in 1987 and suspended in 1992.
On May 11, 2010 JSC Atomstroyexport signed the contract with JSC “Slovenske Elektrarne” on the “turn-key" supply of the systems of in-core instrumentation, measurement of boron concentration and of the subsystem of coolant level measurement in the reactor installation. At the end of June, 2010 the agreement was reached with JSC “Slovenske Elektrarne” on supply of the neutron noise monitoring system inside the reactor, and on February 25, 2011 the corresponding amendment to the contract was signed.
The works should be completed in 2010-2013. In May, 2010 the kick-off meeting with the customer was held, the main issues related to work commencement were coordinated. Monitoring of progress of performance of the sides’ obligations is carried out monthly.
Since 2012 the project has been implementing with the participation of Integrated Company JSC «NIAEP» - JSC ASE.