Project description. The work on construction is carried out on the basis of a contract signed between NIAEP and OJSC Rosenergoatom Concern in 2008. Construction of Kalinin NPP unit 4 started in 2007 and was completed in 2012.
2012 results. The scope of design and exploration work amounted to 147,828.61 thousand rubles in 2012. The key events in the reporting period were the completion of work on the project and commissioning of Kalinin NPP unit 4 in September 2012. The level of the project availability on 2012 was 100% and contribution of the reporting period to the availability level amounted to 8.82%. In 2012 the Integrated Company cooperated with 12 subcontractors during performance of work on the Kalinin NPP project. The total number of staff of the subcontracting organizations amounted to 1,083 people, including 903 workers.
2013 arrangements. Construction is completed.