Kaliningrad Region. Baltic NPP, Generating Units 1 and 2

balt1

Project description. The work on construction of generating units 1 and 2 is carried out on the basis of a contract signed by NIAEP and OJSC Rosenergoatom Concern in 2011. Construction of generating unit 1 started in 2011, it is planned to complete the work on unit 1 in 2017 and on unit 2 in 2018.

2012 results.

For generating units 1 and 2 accordingly:

In 2012 the Integrated Company cooperated with 24 subcontracting organizations during generating units installation on the Baltic NPP project. The total number of staff of the subcontracting organizations amounted to 1,160 people, including 935 workers.

2013 arrangements. By the end of 2013 it is planned that generating unit 1 will be completed to 15.52%, and generating unit 2 to 2.64%. Thus, the 2013 contribution to the availability of units 1 and 2 will amount to 11.37% and 1.48% accordingly.